TIMELINE

FEB 2015:
Spoke to Suresh from the Loan Studio and got verbal approval of ability to apply for a home loan as well as received a loan break down for repayments and contributions. 
Was then introduced to Vera who would be our consultant for the remainder of the process.

FEB 2015:

Visited Warralily Display and signed quote with Brian from Carlisle Homes for the Addison 24 Mk2. 

FEB 2015:

Chose land from Warralily Promenade "Lot 3125, Stage 31, Ackland St, originally to title August 2015.

MAR 2015: 

Paid $1000 deposit to Warralily developer to hold land, paid $1000 deposit to Carlisle Homes for house. Introduced to Nicki our CLE on the phone 

MAR 2015: 

Paid balance of land deposit (5%) to Warralily and signed Contract of Sale for land. Sent Contract of Sale to Conveyancer to review, who would then send to Loan Studio to show the bank. 

MAR 2015: 

Colour browse at Carlisle Homes Spectra Showroom with 'Sally' 

JUNE 2015: 

Colour Selection Appointment 


JUNE 2015: 

Tender Appointment and payment of remainder of 5% to Carlisle Homes 

JUNE 2015:

Told of delay in land titling/settling and new estimate is Sept/Oct 

JULY 2015:

Contract Signing Appointment

JULY 2015: 

Applied for First Home Owners Grant 

JULY 2015: 

Conditional approval from the bank and valuation from the bank for the land/construction comes back in. 

JULY 2015:

Official approval from the bank for Land/Construction home loan. 

AUG 2015:

Post contract variation for Kitchen Pendant lights over island bench 

AUG 2015:

Land Title/Settlement Dates are delayed - New estimate Oct/Nov 

NOV 2015:


Compliance received on the 1st 

NOV 2015:

Land Titled 30th 

DEC 2015:

Land Settles 13th

DEC 2015:

Trades on leave 20th December 

JAN 19th 2015:

Developers Approval 
Received updated floorplans from CH
"Waiting to receive property information back from council, once received CH can obtain engineering and building permit" 

FEB 8th 2015:

Community Infrastructure Levy fee Paid – approx. $900 required as part of your developer requirements. 
Asset Protection Permit – Footpath permit fee of approx. $130
Both paid at council in Geelong. 


MARCH 1st:
Site Start - Site Cut


MARCH 9th:

Drains

MARCH 15th:

Slab Finished

MARCH 23rd:

Frame Stage Complete

APRIL 1st:

Lock Up Stage Starts
Roof Cover Complete
External walls wrapped 
Electrical Rough In



APRIL 16th:

Bricking 3/4 Finished (Awaiting master window from A&L)
Plaster Finished (Cornices and Architraves still to be installed)





APRIL 20th:
Cabinetry Installed in Kitchen/Bathrooms/Laundry 
Bricking Finished on Master and whole house
Internal Doors Delivered
Last Window delivered for master 








APRIL 25th:

Kitchen Cabinetry Completed (Stone still to come)
Master window Installed
Front Door Installed (Still to be stained)
Internal Doors Installed
Officially Locked Out of House




APRIL 30th:
Base render
Architraves
Brick Clean
Waterproofing













MAY 8th:

Painting 3/4 Finished



















MAY 15th:

Painting Complete
Tiling Started
























MAY 22nd:

Stone benchtops installed
Tiling 95% Complete





MAY 27th-30th:
Plumbing complete
Electrical Complete
Data Complete
Heating/Cooling Complete
Shower Screens
















JUNE 1st:

Timber floors complete
Timer cladding complete
Garage door installed 
Pendant Lights Installed
WIR Paintry Fitout
Caulking