SITE VISIT: 27/05/16

We had an emergency family situation back in our hometown, so we had to drive back there on Friday morning. We stopped past the house on the way to take a look and called our SS to organise to take a look inside. The plumbing/electrical/heating/cooling/data has all been done with the exception of the bathroom basins, which were apparently missing for a few days. The flooring is due to start today (Monday 30th) and should be done in a couple of days hopefully. 

Completion Stage:
Brick Clean
Painting
Tiling
Electrical Fitoff
Plumbing Fitoff
Toilets/Basins/Baths/Tapware
Flyscreens
Shelving/Robe Fit out
Splashbacks/Mirrors/Shower Screens
Garage Door
Carpet
Timber Flooring

Collection of Amenities onsite 
Final Builders Clean
Caulking
Final Render Coat
Appliances
Pendants
__________

Touchups
Inspections
Cert of Occupancy
Completion list completed by builder
Bank Valuation
Handover

Here are some photos of where it was at on Friday: 


Sink and Tap are installed in the kitchen YAY! Looks great.


Bathroom vanity tiles are in but not grouted yet

Bath looking shmicko now installed with the taps as well.  

 Front facade feature copper lights are installed, love them! Will look nice when the render colour goes on. 

Theatre wall looking nice. Ensuite sliding door still to go in.

View of the lounge/dining/kitchen 

Kitchen coming together now 

Sink and Tap now installed, looking nice! 

Down lights, heating, cooling and dining table light (to be replaced with fixture after handover) 

Theatre


Heating/cooling thermo controls have been installed. Thinking of puting a plant in this little corner in front of the vent.


Toilets installed

Vanity splashback white subway tiles installed  

Shower head and taps installed 

Main bathroom shower screen still to be installed 

Laundry tap installed and broom cupboad handle 

Master 

 Ensuite vanity - basins, taps, mirror and grout still to come

 Ensuite shower screen, taps and shower head installed

 Delicious ensuite shower rain head with hand held body sprayer. Yasss

 Lounge feature wall

Alfresco fan and down lights installed  

Alfresco outdoor powerpoint installed

Sensor lights installed, but this one needs to be replaced as the left light is broken. 

Sunday, 22 May 2016

SITE VISIT: 22/05/16 Stone Benchtops and Tiling

Looking through the windows again as we are locked out. But the tiling seems to be all done with the exception of the vanity splashback white subway tiles as they were waiting for the stone to go in. Fly screens were also in when we went for a look! 

Also speaking to our SS he said Heating/Cooling/Electrical Fitoffs to be done early this week (23/24/25 May) and Plumbing later this week (25, 26, 27 May) around then. 
Also house clean to be done before our flooring goes in next week. 

Completion Stage:
Brick Clean
Painting
Tiling
Electrical Fitoff
Plumbing Fitoff
Shelving/Robe Fit out
Toilets/Basins/Baths/Tapware
Splashbacks/Mirrors/Shower Screens
Garage Door
Carpet
Timber Flooring
Collection of Amenities onsite 
Final Builders Clean
Flyscreens
Caulking
Final Render Coat
Appliances
Pendants
__________

Touchups
Inspections
Cert of Occupancy
Completion list completed by builder
Bank Valuation
Handover







Wednesday, 18 May 2016

SITE VISIT: 13/05/16 Painting Complete - Tiling Started

Locked out, but some photos through the windows at our finished paint! 

Master Bedroom

Garage 

 Garage

Hallway

 Master 

Ensuite

Spare Bedroom

Study

 Lounge

 Kitchen

Theatre

Sunday, 8 May 2016

SITE VISIT: 08/05/16 Painting

Went for a look on Sunday and the painter rocked up while i was taking photos of the outside and offered to let me in for a look. I asked him why he was working on a Sunday and he said he had worked for the past 3 months straight!! Poor guy. 

So Painting is due to finish on Tuesday 10th May - they have done the first coat on the walls/ceiling and architraves but it will all be cleaned up and finished obviously. The photos i took just give an idea what it looks like at the moment and how the colour looks on the wall. 

I also called Paul our SS today (Monday) to ask about a few things to get rectified;
• Front window next to door is supposed to be frosted as well
• Bit of a wonky wall in between the fridge/pantry space
• Beam above the garage is supposed to be stoney creek (light grey) not Namadji (Dark Grey)
• Pendant lights electricals seem to be very far forward and need to be moved back a bit 

Other than that, everything is looking great!

Tiles are apparently getting delivered Thursday, starting Friday. Cedar for the facade is getting delivered next week and then Fit Offs should start next Wednesday apparently.

 Facade - Garage fascia
(I think they painted the garage beam/fascia monument when it should have been Stony Creek) 

Facade - Garage Fascia has been painted in Monument (Should be stony creek)  

Garage - First coat of paint on walls, ceiling and architraves 

Garage Fascia - Should be stony creek, looks ok though!

 Master bedroom looking in through front window 

Garage View 

Ensuite 

 Master bedroom

 Dining room/Meals area wall

Internal doors being painted in the lounge

Study 

Fridge niche and wine rack 

 Theatre - Painter showed us around and said he thinks it's not a good idea to paint all 4 walls with Western Myall (dark grey) as the room is small and that one wall extends into the hallway, which will be very dark!

Kitchen is looking like a bit of a bomb site at the moment while they paint 

Spare bedroom  

Theatre